TY - JOUR N2 - The article presents the problem of scheduling a multi-stage project with limited availability of resources with the discounted cash flow maximization criterion from the perspective of a contractor. The contractor’s cash outflows are associated with the execution of activities. The client’s payments (cash inflows for the contractor) are performed after completing the agreed project’s stages. The proposed solution for this problem is the use of insertion algorithms. Schedules are generated using forward and backward schedule generation schemes and modified justification techniques. The effectiveness of the proposed procedures is the subject of the examination with the use of standard test instances with additionally defined financial settlements of a project. L1 - http://www.czasopisma.pan.pl/Content/104018/PDF/11-Klimek.pdf L2 - http://www.czasopisma.pan.pl/Content/104018 PY - 2018 IS - No 4 KW - insertion algorithms KW - discounted cash flow KW - resource-constrained project scheduling KW - priorityrules A1 - Klimek, Marcin PB - Production Engineering Committee of the Polish Academy of Sciences, Polish Association for Production Management VL - vol. 9 DA - 2018.12.27 T1 - Insertion algorithms to solve the resource-constrained multi-stage project scheduling problemwith discounted cash flow maximization. UR - http://www.czasopisma.pan.pl/dlibra/publication/edition/104018 T2 - Management and Production Engineering Review ER -